Implementation period: 08.2018-01.2019
The existing Karnobat – Sindel railway line has been in operation for more than sixty years as a single electrified railway line. The alignment along Karnobat – Sindel route is 123 km long and consists of 15 open track sections. By 2004, Karnobat – Sindel railway line was doubled and electrified in three sections (Karnobat – Lozarevo, Prilep – Lyulyakovo and Komunari – Yunak) with a total length of 65.837 km, the traffic in these sections is bidirectional.
The following activities are implemented in the investment proposal:
1) Activity I: Revision and updating of the design solution for track and switch layout of Sindel Shunting Yard;
2) Activity II: Complementary design of the flyover from km 18+560 to km 19+450 in the scope of the section Lozarevo-Zavet;
3) Activity III: Revision and updating of the design solution for Yunak-Sindel open track section.
With the implementation of the project, the total length of the double railway alignment from Karnobat to Sindel will be 110.778 km.